The main challenge of this build was the accessibility. The block was located on a relatively busy road, with the house set about 10m above the road level.
This caused some material delivery issues, however, we were able to overcome this obstacle by planning and completing the majority of the driveway works at the start of the project, allowing for a material delivery and storage area.
The works to the house were then undertaken, at which point we returned to the driveway area, when the finishes were completed to ensure they were not damaged throughout the build.